New Year Sale

Why Buy ASD01 Exam Dumps From Passin1Day?

Having thousands of ASD01 customers with 99% passing rate, passin1day has a big success story. We are providing fully Blue Prism exam passing assurance to our customers. You can purchase Designing Blue Prism Process Solutions (EN) exam dumps with full confidence and pass exam.

ASD01 Practice Questions

Question # 1

A proposed Blue Prism solution with the following properties has been created to automate the payment
processing:
• There will be one Blue Prism process that will perform the steps described above.
• Where a case is an exception the status will be set in Paytex to "Manual Review" in order that the manual
team can pick up the case from Paytex and contact the customer and conclude the case.
• It is anticipated that to meet the SLAs of the expected volumes up to 5 instances of the Blue Prism process
will be required to run concurrently.
• A Blue Prism work queue will be used to host the payments. The queue will be configured for only 1 attempt
per case and the key will be {region} & {source account number}.
• The process will be started by the scheduler at 06:00 and will stop at 05:50

Which of the following are correct? (select 3 responses).
There is a risk that a payment can be duplicated.

A.


There is a risk that a payment can be duplicated.

B.

The process should not be designed to use a Blue Prism Work Queue but use Paytex as the work queue.

C.

The process will not scale i.e. you cannot run multiple instances at the same time

D.

The solution exposes sensitive personal information

E.

The process should not be automated as it uses a third party web application.



B.

The process should not be designed to use a Blue Prism Work Queue but use Paytex as the work queue.


C.

The process will not scale i.e. you cannot run multiple instances at the same time


D.

The solution exposes sensitive personal information




Question # 2

The following Object Design has been created for a mainframe banking application

Which of the following statements about the Object design above are correct? (select 2 responses)

A.

The Add Note action in the "BankHost - Notepad" business object does not require an input for Type as
the process definition document states that Information' will always be selected for this process.

B.

The object design facilitates a scalable design that will reduce the impact of change when the object
layer needs altering

C.

The object design should be simplified by storing all BankHost actions in the same object

D.

There is no need for attach actions to be replicated across all the objects.

E.

The design complies with Blue Prism design best practice.



B.

The object design facilitates a scalable design that will reduce the impact of change when the object
layer needs altering


E.

The design complies with Blue Prism design best practice.




Question # 3

ProSafe credil reference agency retrieves data from bank and other credit providers where customers have
missed payments or gone into default. The data is very sensitive and fed directly into a Blue Prism work queue
via a web service. Blue Prism process must process the data within 4 hours. The Blue Prism solution runs
continuously and each case takes approximately 30 seconds to process. It is expected that an average of 10,000
cases per day will be required and up to 10 Blue Prism robots are available. The Blue Prism solution is shown
below:

For each case the process will access the customer account in the HotRisk system and, where an account
exists, harvest the data which will be fed along with the Work Queue data into a rules engine. The rules engine
is a Blue Prism process that does not interact with any target system. It merely consumes data and. via a
complicated series of decision and choice stages, determines the new customer risk factor.
There is to be no scheduler used. Instead the Process Controllers who work in shifts to provide 24 hour support
will stop and start process instances in line with Work Queue volumes.
As a Blue Prism process solution designer, who is reviewing the solution, which of the following would
concern you? (select 3 responses)

A.

The solution is not scalable.

B.

The process does not have an end stage

C.

The rules engine has been built in a process not an object.

D.

The process opens and closes the HotRisk system for each case

E.

The data is too sensitive for automated processing.



A.

The solution is not scalable.


B.

The process does not have an end stage





Question # 4

A process is required for a client in the banking sector that involves using an application to transfer funds
between accounts A strong security model is in place to prevent any malicious activity but the client is nervous
about the risk of external problems, like a power cut leaving a case in an incomplete state or a fault in the
source data causing a case to be duplicated or an excessively large transfer to be made.
What should be included in the solution design? (select 3 responses)

A.

A different queue for each major processing step

B.

A different process for each major processing step.

C.

A single queue that is cleared of all worked items at the start of each day.

D.

Rules to limit transaction values.

E.

A key value that will uniquely identify queue items.



A.

A different queue for each major processing step


E.

A key value that will uniquely identify queue items.





Question # 5

A process definition document has been produced for a process that interfaces with two applications FirstApp
and Customer Information (CI) The
process requirement is to perform data extraction from FirstApp before performing a number of steps in the CI
application.
It is estimated that to perform the daily case volume within SLA's will require 10 robots Average license time
is approximately 10 minutes, with the
FirstApp steps requiring only 1 minute to perform.
The client has a limited number of licences for the FirstApp application and is reluctant to use 10 of these
licenses to automate the process.
Which of the below is a valid design option for the project?

A.

Automate the end to end process using two Blue Prism processes. Process 1 will perform the FirstApp
tasks. Process 2 will perform the CI tasks Data will be passed from Process 1 to Process 2 via a Blue
Prism Work Queue Process 1 will run on a single robot, with Process 2 running on 9 robots.

B.

Automate the end to end process using two Blue Prism processes Process 1 will perform the FirstApp
tasks. Process 2 will perform the CI tasks. Data will be passed from Process 1 to Process 2 via a
spreadsheet. Process 1 will run on a single robot, with Process 2 running on 9 robots.

C.

Automate the end to end process using a single Blue Prism process which will only be run on a single
robot

D.

Automate the end to end process using a single Blue Prism process which will be run on 10 robots



A.

Automate the end to end process using two Blue Prism processes. Process 1 will perform the FirstApp
tasks. Process 2 will perform the CI tasks Data will be passed from Process 1 to Process 2 via a Blue
Prism Work Queue Process 1 will run on a single robot, with Process 2 running on 9 robots.




Question # 6

The status of a Work Queue can be used as a method of recording what work has been done so far on a Work
Queue item
Please consider the following statements:
1. For Ml, to easily see how far an item has been worked
2 To aid manual working of exceptions, providing the Item Status can inform staff what work is still
outstanding on an item that needs manually completing
3. To enable Work Queue items to be safely retried, a process can use the item status to know which updates
have already been performed so that they are not repeated
4 To record the Customer's Surname
Which of the statements are valid reasons for updating a case status?

A.

2 only

B.

2 and 3 only

C.

1, 2 and 3

D.

1 ,2, 3 and 4



C.

1, 2 and 3




Question # 7

Which of the following statements about using Work Queue designs to split a business process into a multi
part robotic solution is correct?
1. Using multiple Work Queues and Processes for the different stages of the business process is a valid design
option to split a business process into a multi part robotic solution
2 Using a single Work Queue and deferring cases for future processing is a valid design option to split a
business process into a multi part robotic solution
3. Using an item's status to control when to work it is a valid design option to split a business process into a
multi part robotic solution
4. You cannot split a business process into a mufti part robotic solution

A.

1 and 2 Only

B.

4 only

C.

1 and 3

D.

1, 2 and 3



D.

1, 2 and 3




Question # 8

Imagine a DR scenario where the main Production database goes down one afternoon. All processes use work queues and all new work is loaded first thing each morning. The database is backed up regularly but not in real time, so the restored back up will be slightly out of date, say by 1 hour. If the backup was restored, and processes were restarted what would be the effect? (select 2 responses)

A.

The processes would resume with the queue item being worked at the time of the incident

B.

The processes would resume with the next available queue item

C.

The queue item being worked at the time of the incident would be automatically marked as an
exception.

D.

The queue item being worked at the time of the incident would need to be manually marked as an
exception.

E.

The work queue would automatically ensure no cases is duplicated.



B.

The processes would resume with the next available queue item


C.

The queue item being worked at the time of the incident would be automatically marked as an
exception.




ASD01 Dumps
  • Up-to-Date ASD01 Exam Dumps
  • Valid Questions Answers
  • Designing Blue Prism Process Solutions (EN) PDF & Online Test Engine Format
  • 3 Months Free Updates
  • Dedicated Customer Support
  • Solution Designer Pass in 1 Day For Sure
  • SSL Secure Protected Site
  • Exam Passing Assurance
  • 98% ASD01 Exam Success Rate
  • Valid for All Countries

Blue Prism ASD01 Exam Dumps

Exam Name: Designing Blue Prism Process Solutions (EN)
Certification Name: Solution Designer

Blue Prism ASD01 exam dumps are created by industry top professionals and after that its also verified by expert team. We are providing you updated Designing Blue Prism Process Solutions (EN) exam questions answers. We keep updating our Solution Designer practice test according to real exam. So prepare from our latest questions answers and pass your exam.

  • Total Questions: 27
  • Last Updation Date: 16-Jan-2025

Up-to-Date

We always provide up-to-date ASD01 exam dumps to our clients. Keep checking website for updates and download.

Excellence

Quality and excellence of our Designing Blue Prism Process Solutions (EN) practice questions are above customers expectations. Contact live chat to know more.

Success

Your SUCCESS is assured with the ASD01 exam questions of passin1day.com. Just Buy, Prepare and PASS!

Quality

All our braindumps are verified with their correct answers. Download Solution Designer Practice tests in a printable PDF format.

Basic

$80

Any 3 Exams of Your Choice

3 Exams PDF + Online Test Engine

Buy Now
Premium

$100

Any 4 Exams of Your Choice

4 Exams PDF + Online Test Engine

Buy Now
Gold

$125

Any 5 Exams of Your Choice

5 Exams PDF + Online Test Engine

Buy Now

Passin1Day has a big success story in last 12 years with a long list of satisfied customers.

We are UK based company, selling ASD01 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.

We dont have a single unsatisfied Blue Prism customer in this time. Our customers are our asset and precious to us more than their money.

ASD01 Dumps

We have recently updated Blue Prism ASD01 dumps study guide. You can use our Solution Designer braindumps and pass your exam in just 24 hours. Our Designing Blue Prism Process Solutions (EN) real exam contains latest questions. We are providing Blue Prism ASD01 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever Blue Prism update Designing Blue Prism Process Solutions (EN) exam, we also update our file with new questions. Passin1day is here to provide real ASD01 exam questions to people who find it difficult to pass exam

Solution Designer can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with ASD01 dumps. Blue Prism Certifications demonstrate your competence and make your discerning employers recognize that Designing Blue Prism Process Solutions (EN) certified employees are more valuable to their organizations and customers.


We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive Blue Prism exam dumps will enable you to pass your certification Solution Designer exam in just a single try. Passin1day is offering ASD01 braindumps which are accurate and of high-quality verified by the IT professionals.

Candidates can instantly download Solution Designer dumps and access them at any device after purchase. Online Designing Blue Prism Process Solutions (EN) practice tests are planned and designed to prepare you completely for the real Blue Prism exam condition. Free ASD01 dumps demos can be available on customer’s demand to check before placing an order.


What Our Customers Say