Question # 1 Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria? A. Yes, because only Must Have requirements should be fully understood.B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.C. No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.D. No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.
Click for Answer
B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
Answer Description Explanation:
B. Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.
Rationale:
In Agile Project Management, flexibility is key. It is important to prioritize work based on the value it provides and the necessity of the requirement. "Should Have" requirements are important but not critical, and they can be subject to change as the project progresses and as more information becomes available. Deferring the detailed setting of acceptance criteria for a "Should Have" requirement that might be dropped is a practical approach to managing workload and focusing efforts on the most critical aspects of the project first. This approach is in line with Agile's principle of responding to change over following a fixed plan.
Question # 2 Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team? A. Create an email group for the Solution Development Team to collaborate
on ideas.B. Set up a telephone or video conferencing facility so that all members of
the team can collaborate effectively.C. Relocate these employees to a new project area, with a number of desks
where the Solution Development Team can sit together.D. No action required as these employees are located in the same office.
Click for Answer
C. Relocate these employees to a new project area, with a number of desks
where the Solution Development Team can sit together.
Question # 3 Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
'all members of the project understand and accept the DSDM approach'.
What action should the Project Manager take? A. Replace the web developers with experienced Agile practitioners.B. Agree with the statement in the PAQ and keep a close watch on the web
developers throughout the project.C. Organize a training workshop to brief all project-level and Solution
Development Team roles in the Agile approach.D. Accept that the web developers are experts in their field and will be
adopting their own approach throughout the project.
Click for Answer
C. Organize a training workshop to brief all project-level and Solution
Development Team roles in the Agile approach.
Question # 4 Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project? A. Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.B. Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.C. No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.D. No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders'
expectations.
Click for Answer
D. No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders'
expectations.
Question # 5 Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Delivery Plan? A. The Project Manager should include any known constraints associated with planning permission.B. The Project Manager should NOT need to identify any risks this early in the project.C. The approach to the project should be based on the Project Approach Questionnaire responses.D. The Earth Excavations' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.E. The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
Click for Answer
A. The Project Manager should include any known constraints associated with planning permission.E. The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
Answer Description Explanation:
In the context of Agile Project Management, when developing the Delivery Plan during the Feasibility phase, the two statements that best align with Agile principles are:
A. The Project Manager should include any known constraints associated with planning permission.
E. The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.
Here's the rationale:
•A: Recognizing and accounting for known constraints such as planning permission is a key aspect of Agile. It allows for better adaptability and planning around these constraints. Including them early in the Delivery Plan helps ensure that they are considered throughout the project.
•E: Agile emphasizes cross-functional collaboration and stakeholder engagement. The Marketing Director would provide valuable insights into customer needs and market conditions, which are crucial for a successful delivery plan.
Question # 6 Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take? A. Change the end date of the Timebox.B. Ensure that this issue is escalated to the project level roles.C. Amend the end date in the Delivery Plan.D. Accept that the Must Have requirements will not be delivered on time.
Click for Answer
B. Ensure that this issue is escalated to the project level roles.
Question # 7 Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
A. Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.
B. Invite the Marketing Director to create a summary of the content they believe the system should hold and why.
C. Assign ownership of the workshop to the Software Developer.
D. Ask the IT Operations Manager to prepare the agenda for the workshop.
E. Research other hotel reservation systems to form an opinion on what the content should be.
Click for Answer
A. Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.
B. Invite the Marketing Director to create a summary of the content they believe the system should hold and why.
Question # 8 The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time? A. Maintain a tight control on progress, recording all discussions and making
all decisions.B. The Project Manager should do nothing during a Timebox.C. Attend the Daily Stand-up and discuss any problems at the end.D. Update the Team Board with a summary of team progress and the current
status of work.
Click for Answer
C. Attend the Daily Stand-up and discuss any problems at the end.
Answer Description To lead the Solution Development Team effectively during the first Structured Timebox, the Project Manager should:
C. Attend the Daily Stand-up and discuss any problems at the end.
Attending the Daily Stand-up meetings allows the Project Manager to stay informed about the team's progress, challenges, and any blockers they might be facing. It offers an opportunity for the Project Manager to provide support, guidance, and decision-making where necessary, without disrupting the team's autonomy and self-organization. This approach encourages open communication, quick resolution of issues, and maintains the Agile principle of collaboration and continuous improvement. Discussing problems at the end of the meeting ensures that any issues are addressed promptly, keeping the Timebox on track.
Up-to-Date
We always provide up-to-date AgilePM-Practitioner exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our Agile Project Management (AgilePM) Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the AgilePM-Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download AgilePM Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling AgilePM-Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied APMG-International customer in this time. Our customers are our asset and precious to us more than their money.
AgilePM-Practitioner Dumps
We have recently updated APMG-International AgilePM-Practitioner dumps study guide. You can use our AgilePM braindumps and pass your exam in just 24 hours. Our Agile Project Management (AgilePM) Practitioner Exam real exam contains latest questions. We are providing APMG-International AgilePM-Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever APMG-International update Agile Project Management (AgilePM) Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real AgilePM-Practitioner exam questions to people who find it difficult to pass exam
AgilePM can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with AgilePM-Practitioner dumps. APMG-International Certifications demonstrate your competence and make your discerning employers recognize that Agile Project Management (AgilePM) Practitioner Exam certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive APMG-International exam dumps will enable you to pass your certification AgilePM exam in just a single try. Passin1day is offering AgilePM-Practitioner braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download AgilePM dumps and access them at any device after purchase. Online Agile Project Management (AgilePM) Practitioner Exam practice tests are planned and designed to prepare you completely for the real APMG-International exam condition. Free AgilePM-Practitioner dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my APMG-International exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your AgilePM-Practitioner exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your Agile Project Management (AgilePM) Practitioner Exam braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.