Question # 1 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually? A. $31,875
B. $12,550
C. $29,600
D. $13,515
Click for Answer
D. $13,515
Question # 2 A _________contract allows the contractor to freely employ whatever methods and resources it chooses in order to complete the work. A. Guaranteed maximum price
B. Cost reimbursable/Fixed fee
C. Measured unit price
D. Lump-sum/Fixed price
Click for Answer
D. Lump-sum/Fixed price
Question # 3 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs. A. Need satisfaction
B. Belonging needs
C. Self-actualizations
D. Esteem
Click for Answer
C. Self-actualizations
Question # 4 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)? A. Ratio/level of effort
B. Start/finish
C. Units completed
D. Incremental milestone
Click for Answer
A. Ratio/level of effort
Question # 5 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following should be included in the life-cycle cost analysis of a power plant? A. Construction cost, operating cost, maintenance cost
B. Factory expenses, distribution expenses, mark-up
C. Capacity factor, end product units, physical dimensions
D. Resources, work activities, final cost objects
Click for Answer
A. Construction cost, operating cost, maintenance cost
Question # 6 If two alternatives with different useful lives are to be compared considering all costs, which of the following methods is most appropriate?
A. Optimization
B. Net Present Worth
C. Equivalent Uniform Annual Value
D. Future Worth
Click for Answer
C. Equivalent Uniform Annual Value
Question # 7 A task has an early start of day 4. late start of day 14. early finish of day 10. and a late finish of day 20. What is the task's float?
A. 4B. 10C. 20D. 9
Click for Answer
B. 10
Question # 8 Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience. A. Motivation, professionalism
B. Background, attitude
C. Political preference, sense of humor
D. Culture, understanding
Click for Answer
B. Background, attitude
Up-to-Date
We always provide up-to-date CCP exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our Certified Cost Professional (CCP) Exam practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the CCP exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download AACE Certification Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling CCP practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied AACE International customer in this time. Our customers are our asset and precious to us more than their money.
CCP Dumps
We have recently updated AACE International CCP dumps study guide. You can use our AACE Certification braindumps and pass your exam in just 24 hours. Our Certified Cost Professional (CCP) Exam real exam contains latest questions. We are providing AACE International CCP dumps with updates for 3 months. You can purchase in advance and start studying. Whenever AACE International update Certified Cost Professional (CCP) Exam exam, we also update our file with new questions. Passin1day is here to provide real CCP exam questions to people who find it difficult to pass exam
AACE Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with CCP dumps. AACE International Certifications demonstrate your competence and make your discerning employers recognize that Certified Cost Professional (CCP) Exam certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive AACE International exam dumps will enable you to pass your certification AACE Certification exam in just a single try. Passin1day is offering CCP braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download AACE Certification dumps and access them at any device after purchase. Online Certified Cost Professional (CCP) Exam practice tests are planned and designed to prepare you completely for the real AACE International exam condition. Free CCP dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my AACE International exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your CCP exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your Certified Cost Professional (CCP) Exam braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.