Discount Offer

Why Buy CTAL-TM_Syll2012 Exam Dumps From Passin1Day?

Having thousands of CTAL-TM_Syll2012 customers with 99% passing rate, passin1day has a big success story. We are providing fully iSQI exam passing assurance to our customers. You can purchase ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] exam dumps with full confidence and pass exam.

CTAL-TM_Syll2012 Practice Questions

Question # 1

Test Management
Based on the historical data of 5 past and similar projects, you have calculated these
average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new
project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent
in the past projects.
Based on this information only, which of the following statement is certainly true about this
project?
Number of correct responses: 1
K3 3 credits

A.

The code for the new project contains a higher defect density than the code of the past
projects

B.

The number of defects found during the system test phase on the new project is
approximately proportional to the development team effort

C.

40000 LOC have been delivered to system testing (against the 20000 LOC planned by
the project manager)

D.

More LOC than planned have been delivered to system testing with a higher defect
density than the past projects



B.

The number of defects found during the system test phase on the new project is
approximately proportional to the development team effort




Question # 2

Test Management
Which of the following statements about management of product quality risks in mature
organizations with respect to the lifecycle, is true?
Number of correct responses: 1
K2 1 credit

A.

Mature organizations address product quality risks associated to non-functional
characteristics only during the system test phase

B.

Mature organizations are aware that the contribution of testing to analysis of product
quality risks is very important. The analysis should occur throughout the entire lifecycle

C.

Mature organizations don’t waste time identifying the sources of risks. They only focus
on identifying product quality risks

D.

Mature organizations are aware that risk management of product quality risks only
occurs during testing



B.

Mature organizations are aware that the contribution of testing to analysis of product
quality risks is very important. The analysis should occur throughout the entire lifecycle




Question # 3

Test Management
Which of the following statements best describes an appropriate approach for managing
exploratory testing?
Number of correct responses: 1
K2 1 credit

A.

Define very detailed mission statements, which allow testing work to be broken into
sessions of up to 10 minutes duration in which testing is guided by these mission
statements

B.

Break the testing work in 30 to 120 minutes sessions and use properly defined mission
statements consisting of two or three sentences to guide testing during these sessions

C.

Define very generic charters to drive exploratory testing sessions of 2 days where
testers are completely free to decide what to test

D.

Exploratory testing should not be managed because such testing is inherently
unmanageable and not measurable



B.

Break the testing work in 30 to 120 minutes sessions and use properly defined mission
statements consisting of two or three sentences to guide testing during these sessions




Question # 4

Test Management
Which of the following statements, about the test reporting activities for a project adopting
an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
Number of correct responses: 1
K2 1 credit

A.

Test reporting activities can’t be influenced by the use of an iterative lifecycle model with
short iterations

B.

Test reporting activities are not important for projects adopting an iterative lifecycle
model with short iterations

C.

Test reporting activities are less important for projects adopting an iterative life cycle
model with short iterations. They should be performed at the end of the last iteration

D.

Test reporting activities are still important with an iterative lifecycle. The reports can be
used to conduct post-iteration review sessions before starting with the next iteration



D.

Test reporting activities are still important with an iterative lifecycle. The reports can be
used to conduct post-iteration review sessions before starting with the next iteration




Question # 5

Defect Management
Assume you are working on a defect management process to be used by a software
organization to track the current status of the defects reports for several projects.
When a defect is found for investigation a defect report is created in “Opened” state that is
the unique initial state. The defect report status has also a unique finale state that is the
“Closed” state.
The following state transition diagram describes the states of this defect management
process:

where only the initial (“Opened”) and final (“Closed”) states are indicated while the
remaining states (V, W, X, Y, Z) have yet to be named.
Which of the following assignments would you expect to best complete the defect
management process?
Number of correct responses: 1
K3 2 credits

A.

V=Rejected , W=Corrected , X=Validated, Y=Re-Opened, Z=Assigned

B.

V=Assigned, W=Validated , X=Corrected, Y=Re-Opened, Z=Rejected

C.

V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected

D.

V= Corrected, W=Assigned, X=Validated, Y=Corrected, Z=Rejected



C.

V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected




Question # 6

Test Management
Consider an agile team adopting Extreme Programming (XP) with five developers and one
tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
Number of correct responses: 1
K2 1 credit

A.

Developing unit tests

B.

Executing unit tests

C.

Planning and executing tests during the integration test phase to detect interface defects

D.

Supporting the customer in the execution of acceptance testing



D.

Supporting the customer in the execution of acceptance testing




Question # 7

Testing Process
Consider an information system of a Pay-Tv company based on a SOA architecture.
The integrated system currently consists of three core systems:
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a CAS (Conditional Access System) system
all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional
off-the-shelf systems from two different vendors: a SMS (Short Message Service) server
and an IVR (Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality
and that you have a clear proof that the testing performed by the two vendors on their
systems has been unsystematic and unprofessional. This obviously leads to higher quality
risk for the overall integrated system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to
mitigate this risk.
Which of the following answers best describes the test activities (assuming it is possible to
perform all of them) you should plan for?
Number of correct responses: 1
K4 3 credits

A.

You should plan for an informal and minimal acceptance test of the two off-the-shelf
systems and then a single end-to-end test of the overall integrated system

B.

You should directly plan for a single end-to-end test focused on end-to-end tests of the
overall integrated system without an acceptance test of the two off-the-shelf systems

C.

You should plan for two levels: a system integration test and an end-to-end test of the
overall integrated system

D.

You should plan for adequate re-testing of both the systems followed by a system
integration test and an end-to-end test of the overall integrated system



D.

You should plan for adequate re-testing of both the systems followed by a system
integration test and an end-to-end test of the overall integrated system




Question # 8

The following is the unique “critical” quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field
designed to get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been
identified:
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of
bottles from the user
Assume that you have used traceability to determine the logical test cases that cover all the
requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the
REQ-SEL-4 requirement?
Number of correct responses: 1
K3 2 credits

A.

Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are
displayed

B.

Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are
displayed

C.

Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of
bottles" message is displayed

D.

Select a 6-bottles package, then try to insert 7 bottles



C.

Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of
bottles" message is displayed




CTAL-TM_Syll2012 Dumps
  • Up-to-Date CTAL-TM_Syll2012 Exam Dumps
  • Valid Questions Answers
  • ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] PDF & Online Test Engine Format
  • 3 Months Free Updates
  • Dedicated Customer Support
  • ISTQB Pass in 1 Day For Sure
  • SSL Secure Protected Site
  • Exam Passing Assurance
  • 98% CTAL-TM_Syll2012 Exam Success Rate
  • Valid for All Countries

iSQI CTAL-TM_Syll2012 Exam Dumps

Exam Name: ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]
Certification Name: ISTQB

iSQI CTAL-TM_Syll2012 exam dumps are created by industry top professionals and after that its also verified by expert team. We are providing you updated ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] exam questions answers. We keep updating our ISTQB practice test according to real exam. So prepare from our latest questions answers and pass your exam.

  • Total Questions: 65
  • Last Updation Date: 28-Mar-2025

Up-to-Date

We always provide up-to-date CTAL-TM_Syll2012 exam dumps to our clients. Keep checking website for updates and download.

Excellence

Quality and excellence of our ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] practice questions are above customers expectations. Contact live chat to know more.

Success

Your SUCCESS is assured with the CTAL-TM_Syll2012 exam questions of passin1day.com. Just Buy, Prepare and PASS!

Quality

All our braindumps are verified with their correct answers. Download ISTQB Practice tests in a printable PDF format.

Basic

$80

Any 3 Exams of Your Choice

3 Exams PDF + Online Test Engine

Buy Now
Premium

$100

Any 4 Exams of Your Choice

4 Exams PDF + Online Test Engine

Buy Now
Gold

$125

Any 5 Exams of Your Choice

5 Exams PDF + Online Test Engine

Buy Now

Passin1Day has a big success story in last 12 years with a long list of satisfied customers.

We are UK based company, selling CTAL-TM_Syll2012 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.

We dont have a single unsatisfied iSQI customer in this time. Our customers are our asset and precious to us more than their money.

CTAL-TM_Syll2012 Dumps

We have recently updated iSQI CTAL-TM_Syll2012 dumps study guide. You can use our ISTQB braindumps and pass your exam in just 24 hours. Our ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] real exam contains latest questions. We are providing iSQI CTAL-TM_Syll2012 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever iSQI update ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] exam, we also update our file with new questions. Passin1day is here to provide real CTAL-TM_Syll2012 exam questions to people who find it difficult to pass exam

ISTQB can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with CTAL-TM_Syll2012 dumps. iSQI Certifications demonstrate your competence and make your discerning employers recognize that ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] certified employees are more valuable to their organizations and customers.


We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive iSQI exam dumps will enable you to pass your certification ISTQB exam in just a single try. Passin1day is offering CTAL-TM_Syll2012 braindumps which are accurate and of high-quality verified by the IT professionals.

Candidates can instantly download ISTQB dumps and access them at any device after purchase. Online ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] practice tests are planned and designed to prepare you completely for the real iSQI exam condition. Free CTAL-TM_Syll2012 dumps demos can be available on customer’s demand to check before placing an order.


What Our Customers Say