Question # 1 Which of the following are primary features provided by a standard laaS solution? (Select two). A. EncryptionB. StorageC. NetworkingD. User interfaceE. Access
Click for Answer
B. StorageC. Networking
Question # 2 A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using? A. ForcingB. AvoidingC. CompromisingD. Smoothing
Click for Answer
A. Forcing
Answer Description Explanation: Forcing is a conflict resolution technique where the project manager makes a decision unilaterally, without seeking consensus. According to CompTIA Project+, forcing may be used when time is critical, and decisions need to be made promptly.
Question # 3 To gather requirements from stakeholders, the project manager sits down with them and
allows them to discuss freely. Which a following technique is the project manager utilizing? A. Process movingB. BrainstormingC. InterviewD. Focus group
Click for Answer
D. Focus group
Answer Description Explanation: A focus group is a technique that involves bringing together a group of
stakeholders and facilitating a discussion to elicit their opinions, needs, and expectations
about the project. This technique can help to gather requirements from stakeholders in an
interactive and collaborative way1, p. 67
Question # 4 Which of the following aspects are true of agile as compared to waterfall? (Select two). A. Agile works through larger integrated teams.
B. Agile promotes project manager ownership over deliverables.
C. Agile reinforces the importance of comprehensive documentation.
D. Agile has more customer involvement throughout development.
E. Agile is more flexible to allow for changes in scope.
Click for Answer
D. Agile has more customer involvement throughout development.
E. Agile is more flexible to allow for changes in scope.
Answer Description Explanation : Agile is a project management methodology that emphasizes customer
collaboration, feedback, and adaptation throughout the project life cycle. Agile teams work
in short iterations, called sprints, and deliver working increments of the product or service
to the customer for review and approval. Agile teams can also respond to changing
requirements and priorities by adjusting the scope, schedule, or quality of the project12.
Waterfall, on the other hand, is a project management methodology that follows a linear
and sequential process, where each phase of the project must be completed before moving
on to the next one. Waterfall teams work with a fixed scope, schedule, and quality, and
deliver the final product or service to the customer at the end of the project. Waterfall teams
have less customer involvement and flexibility during the project development34.
Question # 5 A project manager will conduct a release on the third Friday of the month. The project
manager has notified users that the application will be unavailable for eight hours. Hence,
users need to save any information in advance. Which of the following is the project
manager most likely conducting? Which of the following should occur when implementing an IT infrastructure change that
takes risks into consideration? A. Approving the change request
B. Developing a rollback plan
C. Gathering necessary resources
D. Defining requirements
Click for Answer
B. Developing a rollback plan
Answer Description Explanation : When implementing an IT infrastructure change that takes risks into
consideration, the project manager should develop a rollback plan. A rollback plan is a
contingency plan that outlines the steps that need to be taken in case the change does not
work as expected. It includes a plan to roll back the changes and restore the system to its
previous state.
The project manager should develop a rollback plan when implementing an IT
infrastructure change that takes risks into consideration. A rollback plan is a contingency
plan that describes how to revert back to the previous state of the system in case of a
failure or disruption during the change implementation. A rollback plan can help to minimize
the impact of the change on the system performance and availability and ensure business
continuity and data integrity.
Question # 6 A project team selected a random sample of patient accounts for testing the deliverable.
The data was masked since it contained patient names. Which of the following describes
this type of data? A. Confidential informationB. Protected health information
C. Personally identifiable information
D. Security clearance
Click for Answer
C. Personally identifiable information
Answer Description Explanation :
Personally identifiable information (PII) is any data that can be used to identify, contact, or
locate a specific individual, either alone or combined with other sources. PII includes
information such as name, address, phone number, email address, social security number,
etc. Patient names are examples of PII, and therefore the data that contains them should
be masked or anonymized to protect the privacy and security of the patients. Confidential
information, protected health information, and security clearance are not types of data, but
rather categories or levels of data sensitivity that may require different degrees of
protection or access control.
Question # 7 A project manager sent equipment to a global project team for testing purposes. Only 70%
of the project team received the equipment for testing. Which of the following
considerations is impacting the rest of the team? A. Quality assurance
B. Organizational branding restrictions
C. State privacy acts
D. Country legal regulations
Click for Answer
D. Country legal regulations
Answer Description Explanation : Country legal regulations. Country legal regulations are impacting the rest of
the team that did not receive the equipment for testing. Country legal regulations are rules
and laws that govern how businesses operate in different countries. They may include
aspects such as customs, tariffs, taxes, import and export restrictions, data protection,
intellectual property rights, and environmental standards. Country legal regulations can
affect the delivery and use of equipment for a global project team and may require
compliance with different procedures and documentation.
Question # 8 Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two). A. Creating a backlogB. Managing the quality of deliverablesC. Updating the issue logD. Performing a risk assessmentE. Validating the deliverables
Click for Answer
E. Validating the deliverables
Up-to-Date
We always provide up-to-date PK0-005 exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our CompTIA Project+ Certification (2025) practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the PK0-005 exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download Project+ Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling PK0-005 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied CompTIA customer in this time. Our customers are our asset and precious to us more than their money.
PK0-005 Dumps
We have recently updated CompTIA PK0-005 dumps study guide. You can use our Project+ braindumps and pass your exam in just 24 hours. Our CompTIA Project+ Certification (2025) real exam contains latest questions. We are providing CompTIA PK0-005 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever CompTIA update CompTIA Project+ Certification (2025) exam, we also update our file with new questions. Passin1day is here to provide real PK0-005 exam questions to people who find it difficult to pass exam
Project+ can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PK0-005 dumps. CompTIA Certifications demonstrate your competence and make your discerning employers recognize that CompTIA Project+ Certification (2025) certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive CompTIA exam dumps will enable you to pass your certification Project+ exam in just a single try. Passin1day is offering PK0-005 braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download Project+ dumps and access them at any device after purchase. Online CompTIA Project+ Certification (2025) practice tests are planned and designed to prepare you completely for the real CompTIA exam condition. Free PK0-005 dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my CompTIA exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your PK0-005 exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your CompTIA Project+ Certification (2025) braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.