Question # 1 Which of the following requires the MOST availability from the business team? A. SDLCB. ScrumC. PRINCE2D. Waterfall
Click for Answer
B. Scrum
Answer Description Explanation: Scrum requires the most availability from the business team among the given
options. Scrum is a popular agile framework that organizes work into short iterations called
sprints, usually lasting one to four weeks. Scrum emphasizes collaboration between teams,
customers, and stakeholders and encourages open communication and transparency
throughout the project lifecycle. Scrum requires frequent involvement and feedback from
the business team through activities such as product backlog refinement, sprint planning,
sprint review, sprint retrospective, and daily scrum meetings.
Question # 2 Which of the following cloud models is designed to provide compute, storage, and
networking resources on demand? A. Software as a serviceB. Infrastructure as a serviceC. Data as a serviceD. Platform as a service
Click for Answer
B. Infrastructure as a service
Answer Description Explanation: Infrastructure as a service (IaaS) is a cloud model that provides on-demand
access to cloud-hosted physical and virtual servers, storage, and networking resources.
IaaS customers can provision, configure, and use these resources as they would use onpremises
hardware, but without the hassle of purchasing, installing, managing, and
maintaining them. The cloud service provider owns, manages, and maintains the hardware
and computing resources in its own data centers, and charges the customers based on
their usage. IaaS is suitable for customers who need flexibility, scalability, and control over
their IT infrastructure, and who want to avoid the high costs and complexity of owning and
operating their own hardware. The other options are not correct because:
Software as a service (SaaS) is a cloud model that provides on-demand access to
ready-to-use, cloud-hosted application software. SaaS customers do not need to
install, update, or maintain the software, as the cloud service provider handles all
the technical aspects. SaaS is suitable for customers who need to access common
applications, such as email, office productivity, or customer relationship
management, without worrying about the underlying infrastructure or platform.
Data as a service (DaaS) is a cloud model that provides on-demand access to
cloud-hosted data sources, such as databases, data warehouses, or data lakes.
DaaS customers can query, analyze, and visualize the data, as well as integrate it
with other applications or services, using APIs or web interfaces. DaaS is suitable
for customers who need to leverage data from various sources, such as social
media, IoT devices, or third-party providers, without having to store, manage, or
process the data themselves.
Platform as a service (PaaS) is a cloud model that provides on-demand access to
a complete, ready-to-use, cloud-hosted platform for developing, running,
maintaining, and managing applications. PaaS customers can use the platform’s
tools, frameworks, libraries, and services to create and deploy applications,
without having to worry about the underlying infrastructure or software. PaaS is
suitable for customers who need to develop, test, and deploy applications quickly
and efficiently, and who want to take advantage of the cloud’s scalability, reliability,
and security features.
Question # 3 Which of the following BEST illustrates how team members with different roles should interact on the team? A. SOWB. WBSC. RACID. PERT
Click for Answer
C. RACI
Answer Description Explanation: RACI is a tool that best illustrates how team members with different roles should interact on the team. RACI is an acronym that stands for responsible, accountable, consulted, and informed. RACI is a type of responsibility assignment matrix (RAM) that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI can help to improve communication, collaboration, and accountability among team members and avoid confusion, duplication, or conflicts3
Question # 4 Which of the following is a test that is done on an existing system to ensure the previous
functionality still works after a change has been made? A. Smoke testingB. Regression testingC. Unit testingD. User acceptance testing
Click for Answer
B. Regression testing
Answer Description Explanation: Regression testing is a type of testing that is done on an existing system to
ensure that the previous functionality still works after a change has been made. Regression
testing is a process of retesting or verifying that a software system or application still
performs as expected after it has been modified or updated with new features, bug fixes,
patches, etc. Regression testing can help to detect any errors or defects that may have
been introduced by the change and ensure that no functionality has been broken or
degraded.
Question # 5 A new project team started work three months ago. The team members are increasing their
work productivity and are comfortable asking for help with tasks. Which of the following
describes the current stage of the project team? A. PerformingB. AdjourningC. FormingD. Norming
Click for Answer
D. Norming
Answer Description Explanation : The current stage of the project team is norming, which is the third stage of
the five stages of team development. In this stage, the team members have resolved their
conflicts and differences, and have established a sense of cohesion and collaboration.
They are more productive, supportive, and cooperative, and they follow the agreed norms
and rules of the team. They also communicate effectively and seek feedback and
assistance from each other. The norming stage is preceded by the forming stage, where
the team members get to know each other and the project goals, and the storming stage,
where the team members experience disagreements and challenges. The norming stage is
followed by the performing stage, where the team members work efficiently and
autonomously towards the project outcomes, and the adjourning stage, where the team
members complete the project and celebrate their achievements.
Question # 6 A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO). A. Company visionB. Global environmentC. Brand valueD. Mission statementE. Portfolio budget
Click for Answer
A. Company visionD. Mission statement
Question # 7 After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented? A. Rollback planB. Release planC. Deployment planD. Contingency plan
Click for Answer
A. Rollback plan
Answer Description Explanation: A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts1. A rollback plan is different from a contingency plan, which is a plan to deal with a specific risk event that may or may not occur2. A release plan and a deployment plan are not relevant to the scenario, as they are used to plan and execute the delivery and installation of the system, not to undo them. Therefore, the correct answer is
A. Rollback plan.
Question # 8 As a result of lessons learned, a project manager convenes a meeting to understand the
poor quality of the project documentation. During the meeting, project team members
provide insights from their perspectives and discussions with group members. Which of the
following is the project team doing? A. Executing the approved contingency planB. Constructing an Ishikawa diagram to determine the root causeC. Using a Pareto chart to prioritize the different causesD. Engaging the senior management team in regard to the issue
Click for Answer
B. Constructing an Ishikawa diagram to determine the root cause
Answer Description Explanation: An Ishikawa diagram, also known as a fishbone diagram, is a tool used to
identify and analyze the root causes of a particular problem. CompTIA Project+ references
this tool as essential for quality management and problem-solving.
Up-to-Date
We always provide up-to-date PK0-005 exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our CompTIA Project+ Certification (2025) practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the PK0-005 exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download Project+ Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling PK0-005 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied CompTIA customer in this time. Our customers are our asset and precious to us more than their money.
PK0-005 Dumps
We have recently updated CompTIA PK0-005 dumps study guide. You can use our Project+ braindumps and pass your exam in just 24 hours. Our CompTIA Project+ Certification (2025) real exam contains latest questions. We are providing CompTIA PK0-005 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever CompTIA update CompTIA Project+ Certification (2025) exam, we also update our file with new questions. Passin1day is here to provide real PK0-005 exam questions to people who find it difficult to pass exam
Project+ can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PK0-005 dumps. CompTIA Certifications demonstrate your competence and make your discerning employers recognize that CompTIA Project+ Certification (2025) certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive CompTIA exam dumps will enable you to pass your certification Project+ exam in just a single try. Passin1day is offering PK0-005 braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download Project+ dumps and access them at any device after purchase. Online CompTIA Project+ Certification (2025) practice tests are planned and designed to prepare you completely for the real CompTIA exam condition. Free PK0-005 dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my CompTIA exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your PK0-005 exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your CompTIA Project+ Certification (2025) braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.