Question # 1 Which of the following is NOT an objective of Initiating a Project?
A. Understanding the scope of what is to be done and the products to be delivered
B. Understanding the roles and responsibilities of the Project Management Team
C. Understand how quality required will be achieved
D. Understand how progress will be monitored and controlled
Click for Answer
B. Understanding the roles and responsibilities of the Project Management Team
Question # 2 Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors) Introduction 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced services. 5. MFH document standards will be used. Records 6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved. Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
A. Must be kept to a minimum.
B. Must be kept to a level acceptable to the Ministry of Food Hygiene.
C. Subject to market conditions.
D. The annual increase to be less than half the rate of inflation
Click for Answer
D. The annual increase to be less than half the rate of inflation
Question # 3 Project Scenario Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of: Design for each month - correctly showing at public holidays and new company logo Selected photographs- 12 professionally-produced photographs, showing different members of staffSelected paper and selected envelope - for printing and mailing the calendar Chosen label design - a competition to design a label will be held as part of this project List of customers - names and addresses of customers to whom the calendar will be sent. The project is currently in initiation and will have two further stages: Stage 2 will include tie activities to: Create the customer fast using information from the Accounts and Marketing departments Confirm compliance with the Data Protection Legislation Create a design for each month - this will be done by the internal creative team Select and appoint a professional photographer Gather photograph design ideas from previous project and agree photographic session schedule Prepare a production cost forecast Select paper and envelope. Stage 3 will include the activities to: Produce and select tie professionally-taken photographs Hold the label design competition and choose the label design Assemble the prepared calendar pack. A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue. It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget. At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?
A. There can be no time tolerances for any of the stages.
B. All of the project level time tolerance can be allocated to stage 2.
C. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.
D. Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.
Click for Answer
B. All of the project level time tolerance can be allocated to stage 2.
Question # 4 During which process would the stage tolerances be set?
A. Controlling a Stage
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Click for Answer
Question # 5 Project Scenario – Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers. ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents. The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses. The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project. The ABC Company standard development model for new courses recommends the following stages: End of the Project scenario. Additional Information: The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training. The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally. The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts. The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company’s IT manager reports to the Operations Director. The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course. The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed. The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality. The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager. The Corporate Document Manager reports to the Central Services Director. She helped establish the company’s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high. The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers. End of the additional information. One of the senior managers of the company that is developing the ‘e-learning course’ has worked with ABC Company before. The team manager for the delivery of the ‘e-learning course’ has looked on ABC Company’s intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project. Is this an appropriate application of the ‘learn from experience’ principle, and why?
A. Yes, because the project involves more than one organization.
B. Yes, because the team manager should actively look for useful information.
C. No, because the senior manager should advise the team manager of any lessons.
D. No, because every project is unique and should deliver specific business objectives
Click for Answer
B. Yes, because the team manager should actively look for useful information.
Question # 6 Scenario: The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process. What additional risk will this place on the project?
A. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
B. These changes will delay stage 3 by three weeks.
C. There is only £70k left in the project change budget.
D. The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.
Click for Answer
A. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
Question # 7 The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.'' In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''. Is this appropriate, and why?
A. Yes, because delivering incrementally will reduce the impact of the threat.
B. Yes, because a risk response needs to be implemented for this major threat.
C. No, because risks responses should be identified as part of the 'plan' step.
D. No, because a risk action should be allocated to implement a response
Click for Answer
B. Yes, because a risk response needs to be implemented for this major threat.
Question # 8 Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors) Introduction 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced services. 5. MFH document standards will be used. Records 6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process. 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved. Which statement applies to the Records section?
A. Delete entry 6 because this information should be included in Stage or Team Plans.
B. Move entry 6 to the Reporting section because the information should be used to report on quality activities.
C. Delete entry 7 because this should be included in the Configuration Management Strategy.
D. Delete entry 8 because the results of quality reviews are recorded in the Quality Register
Click for Answer
C. Delete entry 7 because this should be included in the Configuration Management Strategy.
Up-to-Date
We always provide up-to-date PRINCE2-Practitioner exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our PRINCE2 Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the PRINCE2-Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download PRINCE2 Certification Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling PRINCE2-Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied PRINCE2 customer in this time. Our customers are our asset and precious to us more than their money.
PRINCE2-Practitioner Dumps
We have recently updated PRINCE2 PRINCE2-Practitioner dumps study guide. You can use our PRINCE2 Certification braindumps and pass your exam in just 24 hours. Our PRINCE2 Practitioner Exam real exam contains latest questions. We are providing PRINCE2 PRINCE2-Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever PRINCE2 update PRINCE2 Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real PRINCE2-Practitioner exam questions to people who find it difficult to pass exam
PRINCE2 Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PRINCE2-Practitioner dumps. PRINCE2 Certifications demonstrate your competence and make your discerning employers recognize that PRINCE2 Practitioner Exam certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive PRINCE2 exam dumps will enable you to pass your certification PRINCE2 Certification exam in just a single try. Passin1day is offering PRINCE2-Practitioner braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download PRINCE2 Certification dumps and access them at any device after purchase. Online PRINCE2 Practitioner Exam practice tests are planned and designed to prepare you completely for the real PRINCE2 exam condition. Free PRINCE2-Practitioner dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my PRINCE2 exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your PRINCE2-Practitioner exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your PRINCE2 Practitioner Exam braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.