Question # 1 Which project status defaults the project condition to On Target? A. In ProgressB. IdeaC. New
Click for Answer
A. In Progress
Answer Description Explanation:
In Adobe Workfront, when a project is set to "In Progress," the default project condition is marked as "On Target." This reflects that the project is actively being worked on and progressing as expected without any significant issues or delays. The "On Target" condition is designed to signal that the project is meeting the planned timelines and performance metrics.
TheNewandIdeastatuses are preliminary stages where active progress or development has not started yet, and thus these statuses would not set the project condition to "On Target." Instead, they may represent an early phase of consideration or planning, where progress and targets have not been set in motion.
This is an essential feature within Workfront for project management, allowing teams to understand at a glance whether a project is moving as planned or if it requires attention based on predefined thresholds for performance or timing.
For further detailed information, please refer to the Adobe Workfront documentation on project statuses and conditions, which elaborates on how different statuses affect project tracking and reporting.
Question # 2 Which field is used to create a milestone step on a milestone path in the Setup area? A. StatusB. DescriptionC. Key
Click for Answer
C. Key
Answer Description Explanation:
In Adobe Workfront, when creating aMilestone Stepwithin the Setup area, theKeyfield is essential as it serves as a unique identifier for each milestone step. It is used to define the specific step within a milestone path that can be associated with tasks in a project. TheStatusandDescriptionfields are not used for creating the milestone step itself but are more relevant for defining attributes or metadata.
Question # 3 What is unique to a Scrum iteration? A. Backlog of stories and issuesB. Workload Balancer for assigning users to tasksC. Burndown Chart
Click for Answer
C. Burndown Chart
Answer Description Explanation:
A Burndown Chart is a visual representation of work remaining versus time in a Scrum iteration. It is unique to agile methodologies like Scrum and is used to track the team's progress during a sprint. The chart helps teams visualize how much work is left to complete the sprint goal, making it a critical tool in Scrum.
Question # 4 Which date type should an assignee update to change the completion date of a task? A. Actual Completion DateB. Commit DateC. Planned Completion DateD. Projected Start Date
Click for Answer
C. Planned Completion Date
Answer Description Explanation:
In Workfront, to update the planned completion of a task, the assignee should modify the "Planned Completion Date." This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the "Planned Completion Date" adjusts the task's projected timeline and allows for a recalculation of project dependencies.
Question # 5 Which two options are available with Workfront reports? (Choose two.) A. A chart report that references a multi-select custom fieldB. Planned date-based calendar reportsC. Filters with a custom groupingD. An object name with more than 500 characters
Click for Answer
B. Planned date-based calendar reportsC. Filters with a custom grouping
Answer Description Explanation:
In Adobe Workfront,Planned date-based calendar reportsare commonly used to visualize project timelines, milestones, and deadlines. They help teams plan and manage workloads based on dates and other time-related factors.
Filters with custom groupingallow users to customize their reports by organizing data in a meaningful way, tailored to specific project or team requirements. Custom groupings enhance the clarity of reports by categorizing data based on selected criteria.
The other options are not correct because Workfront does not support reports that reference multi-select custom fields in a chart format, nor does it allow object names longer than 500 characters.
Question # 6 The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility? A. A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.B. A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.C. A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.
Click for Answer
C. A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.
Answer Description Explanation:
For executive-level reporting, a program report grouped by department provides a holistic view of ongoing initiatives. This includes the health of programs, urgency, and alignment with business goals. This type of report is essential for leadership teams to assess overall performance and make informed decisions that align with the company’s strategic objectives.
Question # 7 The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates? A. Start No Later ThanB. Must Start OnC. As Late As Possible
Click for Answer
C. As Late As Possible
Answer Description Explanation:
In Workfront, the "As Late As Possible" task constraint ensures that tasks are scheduled as close to the project’s end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.
Question # 8 A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days? A. Change the Task Duration Type to Effort DrivenB. Change the Task Duration Type to Calculated WorkC. Change the Task Constraint to Fixed DatesD. Change the Task Constraint to As Soon As Possible
Click for Answer
B. Change the Task Duration Type to Calculated Work
Answer Description Explanation:
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.
Up-to-Date
We always provide up-to-date AD0-E903 exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our Adobe Workfront Project Manager Professional practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the AD0-E903 exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download Adobe Workfront Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling AD0-E903 practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied Adobe customer in this time. Our customers are our asset and precious to us more than their money.
AD0-E903 Dumps
We have recently updated Adobe AD0-E903 dumps study guide. You can use our Adobe Workfront braindumps and pass your exam in just 24 hours. Our Adobe Workfront Project Manager Professional real exam contains latest questions. We are providing Adobe AD0-E903 dumps with updates for 3 months. You can purchase in advance and start studying. Whenever Adobe update Adobe Workfront Project Manager Professional exam, we also update our file with new questions. Passin1day is here to provide real AD0-E903 exam questions to people who find it difficult to pass exam
Adobe Workfront can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with AD0-E903 dumps. Adobe Certifications demonstrate your competence and make your discerning employers recognize that Adobe Workfront Project Manager Professional certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive Adobe exam dumps will enable you to pass your certification Adobe Workfront exam in just a single try. Passin1day is offering AD0-E903 braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download Adobe Workfront dumps and access them at any device after purchase. Online Adobe Workfront Project Manager Professional practice tests are planned and designed to prepare you completely for the real Adobe exam condition. Free AD0-E903 dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my Adobe exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your AD0-E903 exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your Adobe Workfront Project Manager Professional braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.