Question # 1 Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes: There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find. In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution. The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale. A number of alternatives were explored, including: 20% discount for all repeat customers - not cost-effective and very short term A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year A series of television and press advertisements· was too expensive A direct mail shot to all customers - benefit would be short term Creation of an internet website - would not suit all customers The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur. Which 2 statements correctly define a Business Case risk which should be recorded under the Major risks heading?
A. Operational costs will increase as a result of the recruitment campaign.
B. The prepared calendar pack is to be delivered to the printers by the first week in December.
C. If the calendar quality is poor customers will not use it, creating the reverse effect and reducing orders further.
D. If any competitors launch a calendar at the same time this will reduce the impact of the MNO calendar and benefits will be reduced.
E. Staff morale will improve as a result of the promotional calendar
Click for Answer
C. If the calendar quality is poor customers will not use it, creating the reverse effect and reducing orders further.
D. If any competitors launch a calendar at the same time this will reduce the impact of the MNO calendar and benefits will be reduced.
Question # 2 Having completed designing the plan, in which order should the next steps take place to produce a plan? 1. Prepare Estimates 2. Define and analyze Products 3. Prepare the schedule 4. Identify activities and dependencies
A. 4, 3, 1
B. 4, 2, 1, 3
C. 4, 3, 2, 1
D. 2, 4, 1, 3
Click for Answer
Question # 3 Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered Do nothing. Re-engineer selected business functions. Outsource selected business functions. The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were: One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division. A 10-year service contract should be agreed with the selected service provider. The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project: Use PRINCE2. Set up the project with 4 management stages: Stage 1. Standard PRINCE2 initiation activities. Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider. Stage 3. Request and evaluate proposals, select service provider and agree contract. Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period. Initial estimates indicated that the project would cost £2.5m and take two years to complete. MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years. The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs. Which 2 statements should be recorded under the Major risks heading?
A. Due to market conditions a suitable service provider may not be found, possibly leading to premature closure of the project. difficult to transfer staff to the selected service provider
B. Owing to employment contract changes staff may resist outsourcing, which would make it . MFH's operations may be reduced and the 1a-year contract may not achieve its estimated value of £80m, which would reduce the service provider's profit.
C. The initial estimates, taken from the feasibility study report, indicate that the project will take two years to complete, which means that the business problems would remain for this period.
D. The management stages recommended by the consultants may not be appropriate, resulting in confusion in planning.
Click for Answer
B. Owing to employment contract changes staff may resist outsourcing, which would make it . MFH's operations may be reduced and the 1a-year contract may not achieve its estimated value of £80m, which would reduce the service provider's profit.
D. The management stages recommended by the consultants may not be appropriate, resulting in confusion in planning.
Question # 4 Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors) Introduction 1. This document defines the approach to be taken to achieve the required quality levels during the project. 2. The Project Board will have overall responsibility for the Quality Management Strategy. 3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards 4. The selected service provider will operate to industry standards for providing outsourced services. 5. MFH document standards will be used. Records 6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities. 7. Configuration Item Records will be maintained for each product to describe its status, version and variant. 8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities 9. The DIT will check that the employment contracts for outsourced staff adhere to employment law. 10. Team Managers will provide details of quality checks that have been carried out. 11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process 12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved. The service level agreement contains a number of technical terms that are missing from its glossary of terms.
A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Raise an issue (request for change).
D. No action required.
Click for Answer
A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days tolerance.
Question # 5 A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now. The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced. The contract is to be reviewed and Portraits Ltd reminded of their agreement. The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Which 2 statements should be recorded under either the Records or Reporting headings?
A. Project Support will maintain the Risk Register.
B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.
C. The Change Authority will report monthly to the Project Manager on the status of the change budget.
D. Risks that are likely to occur within the next two weeks should be recorded as imminent.
E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.
Click for Answer
B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.
C. The Change Authority will report monthly to the Project Manager on the status of the change budget.
Question # 6 Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered: Do nothing. Re-engineer selected business functions. Outsource selected business functions. The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were: One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division. A 10-year service contract should be agreed with the selected service provider. The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project: Use PRINCE2. Set up the project with 4 management stages: Stage 1. Standard PRINCE2 initiation activities. Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider. Stage 3. Request and evaluate proposals, select service provider and agree contract. Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period. Initial estimates indicated that the project would cost £2.5m and take two years to complete. MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years. The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs. Which 2 statements should be recorded under the Expected dis-benefits heading?
A. An investment of £2.5m is required.
B. Staff morale will be negatively affected.
C. The project will take two years to deliver.
D. Staff may lose the opportunity to work in Information Technology.
E. MFH will lose direct control over the outsourced business functions.
Click for Answer
C. The project will take two years to deliver.
E. MFH will lose direct control over the outsourced business functions.
Answer Description http://www.whatisprince2.net/prince2-theme-business-case.php
Question # 7 PRINCE2 proposes 3 levels of Plan, which are they?
A. Initiation, Project and Stage Plans
B. Project, Stage and Exception Plans
C. Initiation, Project and Benefit Review Plans
D. Project, Stage and Team Plans
Click for Answer
D. Project, Stage and Team Plans
Question # 8 Which of the following reports does not contain any information on risk?
A. Issue Report
B. Highlight report
C. Lessons Report
D. End Stage Report
Click for Answer
Up-to-Date
We always provide up-to-date PRINCE2 Practitioner exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our PRINCE2 Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the PRINCE2 Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download PRINCE2 Certification Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling PRINCE2 Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied PRINCE2 customer in this time. Our customers are our asset and precious to us more than their money.
PRINCE2 Practitioner Dumps
We have recently updated PRINCE2 PRINCE2 Practitioner dumps study guide. You can use our PRINCE2 Certification braindumps and pass your exam in just 24 hours. Our PRINCE2 Practitioner Exam real exam contains latest questions. We are providing PRINCE2 PRINCE2 Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever PRINCE2 update PRINCE2 Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real PRINCE2 Practitioner exam questions to people who find it difficult to pass exam
PRINCE2 Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PRINCE2 Practitioner dumps. PRINCE2 Certifications demonstrate your competence and make your discerning employers recognize that PRINCE2 Practitioner Exam certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive PRINCE2 exam dumps will enable you to pass your certification PRINCE2 Certification exam in just a single try. Passin1day is offering PRINCE2 Practitioner braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download PRINCE2 Certification dumps and access them at any device after purchase. Online PRINCE2 Practitioner Exam practice tests are planned and designed to prepare you completely for the real PRINCE2 exam condition. Free PRINCE2 Practitioner dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my PRINCE2 exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your PRINCE2 Practitioner exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your PRINCE2 Practitioner Exam braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.