New Year Sale

Why Buy PRINCE2 Practitioner Exam Dumps From Passin1Day?

Having thousands of PRINCE2 Practitioner customers with 99% passing rate, passin1day has a big success story. We are providing fully PRINCE2 exam passing assurance to our customers. You can purchase PRINCE2 Practitioner Exam exam dumps with full confidence and pass exam.

PRINCE2 Practitioner Practice Questions

Question # 1



Question # 2

It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that without the calendar the company is going to experience
difficulties recovering its decline in orders, and alternative solutions are required if the company is
going to recover its position?

A.

 Benefits Review Plan

B.

Exception Report

C.

End Project Report

D.

Risk Register



C.

End Project Report




Question # 3

During which process would the stage tolerances be set?

A.

Controlling a Stage

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Directing a Project



D.

Directing a Project




Question # 4

It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the same time
was identified at the beginning of the project but the assessment of this risk appears to have been
poor?

A.

 Issue Register

B.

Follow-on action recommendations

C.

Lessons Report

D.

Risk Register



C.

Lessons Report




Question # 5

Which of the following statements is FALSE regarding the Continued Business Justification?

A.

The justification for the project must remain the same throughout the project

B.

The justification for the project should remain valid

C.

 The justification for the project may change

D.

 If the project is no longer justified it should be stopped



B.

The justification for the project should remain valid




Question # 6

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer system?

A.

Must be subject to regular back-ups.

B.

Planned periods of shutdowns of the computer system must be kept to a minimum.

C.

No (zero) loss of system functionality.

D.

Back-up of data must be kept until the data is no longer needed.



C.

No (zero) loss of system functionality.




Question # 7

Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term
A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
A series of television and press advertisements· was too expensive
A direct mail shot to all customers - benefit would be short term
Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Which 2 statements should be recorded under the Expected benefits heading?

A.

Increase orders by at least 10% with a minimum of 10 further orders from the list of prospective
customers within 12 months.

B.

 It will be similar to calendars sent out in previous years

C.

The Marketing department believes that the benefits of a good company image, as portrayed by
a successful calendar, will last into a second year and bring the same increase in orders.

D.

The calendar will contain photos of both staff and company products.

E.

The Marketing department want a very high quality, glossy product as they believe this will be
more appealing to customers.



A.

Increase orders by at least 10% with a minimum of 10 further orders from the list of prospective
customers within 12 months.


C.

The Marketing department believes that the benefits of a good company image, as portrayed by
a successful calendar, will last into a second year and bring the same increase in orders.




Question # 8

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no Project Brief. How can there be a common understanding of the desired outcomes for
the prepared calendar pack?

A.

The simple Project Initiation Documentation contains the Quality Management Strategy. This
contains details of the acceptance criteria for this project.

B.

The Project Brief should have been produced and approved before the project progressed into
the initiation stage.

C.

The simple Project Initiation Documentation contains the project definition.



C.

The simple Project Initiation Documentation contains the project definition.




PRINCE2 Practitioner Dumps
  • Up-to-Date PRINCE2 Practitioner Exam Dumps
  • Valid Questions Answers
  • PRINCE2 Practitioner Exam PDF & Online Test Engine Format
  • 3 Months Free Updates
  • Dedicated Customer Support
  • PRINCE2 Certification Pass in 1 Day For Sure
  • SSL Secure Protected Site
  • Exam Passing Assurance
  • 98% PRINCE2 Practitioner Exam Success Rate
  • Valid for All Countries

PRINCE2 PRINCE2 Practitioner Exam Dumps

Exam Name: PRINCE2 Practitioner Exam
Certification Name: PRINCE2 Certification

PRINCE2 PRINCE2 Practitioner exam dumps are created by industry top professionals and after that its also verified by expert team. We are providing you updated PRINCE2 Practitioner Exam exam questions answers. We keep updating our PRINCE2 Certification practice test according to real exam. So prepare from our latest questions answers and pass your exam.

  • Total Questions: 190
  • Last Updation Date: 16-Jan-2025

Up-to-Date

We always provide up-to-date PRINCE2 Practitioner exam dumps to our clients. Keep checking website for updates and download.

Excellence

Quality and excellence of our PRINCE2 Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.

Success

Your SUCCESS is assured with the PRINCE2 Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!

Quality

All our braindumps are verified with their correct answers. Download PRINCE2 Certification Practice tests in a printable PDF format.

Basic

$80

Any 3 Exams of Your Choice

3 Exams PDF + Online Test Engine

Buy Now
Premium

$100

Any 4 Exams of Your Choice

4 Exams PDF + Online Test Engine

Buy Now
Gold

$125

Any 5 Exams of Your Choice

5 Exams PDF + Online Test Engine

Buy Now

Passin1Day has a big success story in last 12 years with a long list of satisfied customers.

We are UK based company, selling PRINCE2 Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.

We dont have a single unsatisfied PRINCE2 customer in this time. Our customers are our asset and precious to us more than their money.

PRINCE2 Practitioner Dumps

We have recently updated PRINCE2 PRINCE2 Practitioner dumps study guide. You can use our PRINCE2 Certification braindumps and pass your exam in just 24 hours. Our PRINCE2 Practitioner Exam real exam contains latest questions. We are providing PRINCE2 PRINCE2 Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever PRINCE2 update PRINCE2 Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real PRINCE2 Practitioner exam questions to people who find it difficult to pass exam

PRINCE2 Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PRINCE2 Practitioner dumps. PRINCE2 Certifications demonstrate your competence and make your discerning employers recognize that PRINCE2 Practitioner Exam certified employees are more valuable to their organizations and customers.


We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive PRINCE2 exam dumps will enable you to pass your certification PRINCE2 Certification exam in just a single try. Passin1day is offering PRINCE2 Practitioner braindumps which are accurate and of high-quality verified by the IT professionals.

Candidates can instantly download PRINCE2 Certification dumps and access them at any device after purchase. Online PRINCE2 Practitioner Exam practice tests are planned and designed to prepare you completely for the real PRINCE2 exam condition. Free PRINCE2 Practitioner dumps demos can be available on customer’s demand to check before placing an order.


What Our Customers Say